Phase 2: Business Blueprint
In this phase scope of the R/3 implementation is defined & Business Blueprint is created. Business Blueprint is a detailed documentation of company’s requirements.
Various tools are used in this phase.
• AcceleratedSAP Implementation Assistant
• Question & Answer Database (Q&Adb)
• Business Process Master List (BPML)
• R/3 Structure Modeler
• Business Navigator and external modeling tools
Project Management:
Activities in this work package are:
• Conducting Status meeting for project team
• Conducting steering committee meetings
• General project management
• Addressing organizational issues relating to organizational change management.
Other activities include:
• Project Team Training
• Developing the System Environment
• Defining Organizational Structure
• Defining the Business processes
R/3 reference model can be used for
• Comparing the standard functionality with your companies own organizational requirements
• Creating documentation for the conceptual design
• Optimizing business processes
• Training the project team and users
• Writing user documentation
Question and Answer Database can be used to determine
• The Baseline Scope
• Cycle Plan
• Integration test Plan